Dept. of Trans. PROGRESS Serial No. Contract No. 25-295-09-01 07-316004 PROGRESS PAYMENT VOUCHER %complete: %time: 76% 77% Location: Federal Project: 07-LA-14-R60.7/R77.0 NONE Progress payment No. 030 Payment period ending: 10-20-25 GUY F ATKINSON CONSTRUCTION LLC 611 ANTON BLVD #1100 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 111,093,658.08 4,371,215.59 2. a. Extra Work 12,014,694.04 45,842.81 b. Adustment Comp. 611,287.69 -192,028.36 3. Materials on Hand 1,086,639.26 -96,294.44 4. Earned Subject to Retention 124,806,279.07 4,128,735.60 5. Mobilization 11,388,250.00 0.00 6. Total Work Completed 135,107,889.81 7. Deductions -14,045.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 136,180,484.07 4,128,735.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,128,735.60