Dept. of Trans. PROGRESS Serial No. Contract No. 20-113-12-31 07-316504 PROGRESS PAYMENT VOUCHER %complete: %time: 10% 13% Location: Federal Project: 07-VEN-118-R24.1/R29.7 HSNH-P118(67) Progress payment No. 003 Payment period ending: 04-20-20 BOSCO CONSTRUCTORS INC 21353 MAYALL ST CHATSWORTH CA 91311 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 178,701.85 122,332.91 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 178,701.85 122,332.91 5. Mobilization 80,598.18 80,598.18 6. Total Work Completed 259,300.03 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 259,300.03 202,931.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 202,931.09