Dept. of Trans. PROGRESS Serial No. Contract No. 20-022-13-58 07-317004 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 100% Location: Federal Project: 07-LA-14-R30.6/R30.6 CNHG-P014(77) Progress payment No. 006 Payment period ending: 01-20-20 DEANGELO BROTHERS LLC 100 NORTH CONAHAN DR HAZLETON PA 18201 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 417,770.52 37,102.09 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 417,770.52 37,102.09 5. Mobilization 28,119.81 0.00 6. Total Work Completed 445,890.33 7. Deductions -118,800.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 327,090.33 36,102.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 36,102.09