Dept. of Trans. PROGRESS Serial No. Contract No. 21-111-10-16 07-317304 PROGRESS PAYMENT VOUCHER %complete: %time: 25% 11% Location: Federal Project: 07-LA-60-0.0/R21.5 ACNH-P060(158) Progress payment No. 002 Payment period ending: 04-20-21 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 398,817.00 308,162.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 121,052.00 68,277.00 4. Earned Subject to Retention 519,869.00 376,439.00 5. Mobilization 103,550.00 49,050.00 6. Total Work Completed 502,367.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 623,419.00 425,489.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 425,489.00