Dept. of Trans. PROGRESS Serial No. Contract No. 21-204-10-06 07-317304 PROGRESS PAYMENT VOUCHER %complete: %time: 38% 49% Location: Federal Project: 07-LA-60-0.0/R21.5 ACNH-P060(158) Progress payment No. 004 Payment period ending: 07-20-21 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 684,292.43 41,510.03 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 106,340.55 -5,987.45 4. Earned Subject to Retention 790,632.98 35,522.58 5. Mobilization 103,550.00 0.00 6. Total Work Completed 787,842.43 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 894,182.98 35,522.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 35,522.58