Dept. of Trans. PROGRESS Serial No. Contract No. 22-081-09-42 07-317304 PROGRESS PAYMENT VOUCHER %complete: %time: 77% 95% Location: Federal Project: 07-LA-60-0.0/R21.5 ACNH-P060(158) Progress payment No. 008 Payment period ending: 03-20-22 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,470,637.41 297,668.20 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -126,565.55 4. Earned Subject to Retention 1,470,637.41 171,102.65 5. Mobilization 109,000.00 0.00 6. Total Work Completed 1,579,637.41 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,579,637.41 181,102.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 181,102.65