Dept. of Trans. PROGRESS Serial No. Contract No. 21-171-15-09 07-317504 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 90% Location: Federal Project: 07-LA-5-11.0/14.0 NONE Progress payment No. 012 Payment period ending: 06-20-21 SHIMMICK CONSTRUCTION CO. INC 8201 EDGEWATER DR #202 OAKLAND CA 94621 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,591,115.00 11,207.50 2. a. Extra Work 77,125.65 0.00 b. Adustment Comp. 102,416.39 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,770,657.04 11,207.50 5. Mobilization 510,000.00 0.00 6. Total Work Completed 5,280,657.04 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,280,657.04 11,207.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,207.50