Dept. of Trans. PROGRESS Serial No. Contract No. 22-327-14-06 07-317904 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 46% Location: Federal Project: 07-LA-101-20.0/20.0 NONE Progress payment No. 004 Payment period ending: 11-20-22 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIR CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 563,278.34 2,975.00 2. a. Extra Work 53,802.48 2,407.48 b. Adustment Comp. 115,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 732,080.82 5,382.48 5. Mobilization 130,000.00 0.00 6. Total Work Completed 862,080.82 7. Deductions -2,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 860,080.82 3,382.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,382.48