Dept. of Trans. PROGRESS Serial No. Contract No. 23-027-08-58 07-317904 PROGRESS PAYMENT VOUCHER %complete: %time: 61% 46% Location: Federal Project: 07-LA-101-20.0/20.0 NONE Progress payment No. 006 Payment period ending: 01-20-23 BEADOR CONSTRUCTION COMPANY INC 2900 BRISTOL ST #D204 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 660,038.69 30,908.90 2. a. Extra Work 86,431.24 32,628.76 b. Adustment Comp. 115,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 861,469.93 63,537.66 5. Mobilization 130,000.00 0.00 6. Total Work Completed 991,469.93 7. Deductions -2,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 989,469.93 63,537.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 63,537.66