Dept. of Trans. PROGRESS Serial No. Contract No. 18-114-15-16 07-318004 PROGRESS PAYMENT VOUCHER %complete: %time: 13% 28% Location: Federal Project: 07-LA-10-22.3/28.2 ACIM-010-1(838) Progress payment No. 003 Payment period ending: 04-20-18 SPECTRUM CONSTRUCTION GROUP INC 32 EDELMAN IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 248,683.25 130,879.20 2. a. Extra Work 3,452.00 3,452.00 b. Adustment Comp. 3. Materials on Hand 87,075.17 0.00 4. Earned Subject to Retention 339,210.42 134,331.20 5. Mobilization 126,056.25 42,018.75 6. Total Work Completed 378,191.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 465,266.67 176,349.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 176,349.95