Dept. of Trans. PROGRESS Serial No. Contract No. 22-234-08-38 07-318204 PROGRESS PAYMENT VOUCHER %complete: %time: 42% 41% Location: Federal Project: 07-VEN-1-4.0/4.2 NONE Progress payment No. 011 Payment period ending: 08-20-22 FLATIRON-DRILL TECH A JOINT VENTURE 12121 SCRIPPS SUMMIT DRIVE #4 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,715,943.11 2,013,815.19 2. a. Extra Work 649,404.01 0.00 b. Adustment Comp. 3. Materials on Hand 1,834,594.32 -94,918.19 4. Earned Subject to Retention 16,199,941.44 1,918,897.00 5. Mobilization 3,997,600.00 0.00 6. Total Work Completed 18,362,947.12 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 20,197,541.44 1,918,897.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,918,897.00