Dept. of Trans. PROGRESS Serial No. Contract No. 23-356-10-58 07-318204 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 90% Location: Federal Project: 07-VEN-1-4.0/4.2 NONE Progress payment No. 027 Payment period ending: 12-20-23 FLATIRON-DRILL TECH A JOINT VENTURE 12121 SCRIPPS SUMMIT DRIVE #4 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 36,848,713.07 588,656.30 2. a. Extra Work 4,574,941.70 12,725.25 b. Adustment Comp. 272,658.58 0.00 3. Materials on Hand 140,204.82 -38,225.41 4. Earned Subject to Retention 41,836,518.17 563,156.14 5. Mobilization 4,208,000.00 0.00 6. Total Work Completed 45,904,313.35 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 46,044,518.17 563,156.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 563,156.14