Dept. of Trans. PROGRESS Serial No. Contract No. 21-141-10-58 07-318804 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 61% Location: Federal Project: 07-LA-605-23.4/23.6 CIMG-6052(994) Progress payment No. 004 Payment period ending: 05-20-21 LOS ANGELES ENGINEERING INC. 633 N. BARRANCA AVENUE COVINA CA 91723 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 678,911.05 324,031.55 2. a. Extra Work 34,994.34 34,994.34 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 713,905.39 359,025.89 5. Mobilization 56,000.00 2,800.00 6. Total Work Completed 769,905.39 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 769,905.39 361,825.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 361,825.89