Dept. of Trans. PROGRESS Serial No. Contract No. 22-203-14-30 07-319104 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 44% Location: Federal Project: 07-LA-91-R11.8/R11.8 NONE Progress payment No. 003 Payment period ending: 07-20-22 RV CONCRETE INC 605 E COMMERCIAL ST ANAHEIM CA 92801 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 612,853.05 -13,486.50 2. a. Extra Work 9,951.33 9,951.33 b. Adustment Comp. 3. Materials on Hand 28,866.80 28,866.80 4. Earned Subject to Retention 651,671.18 25,331.63 5. Mobilization 199,500.00 0.00 6. Total Work Completed 822,304.38 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 851,171.18 25,331.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 25,331.63