Dept. of Trans. PROGRESS Serial No. Contract No. 22-234-09-41 07-319104 PROGRESS PAYMENT VOUCHER %complete: %time: 38% 59% Location: Federal Project: 07-LA-91-R11.8/R11.8 NONE Progress payment No. 004 Payment period ending: 08-20-22 RV CONCRETE INC 605 E COMMERCIAL ST ANAHEIM CA 92801 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 720,661.37 107,808.32 2. a. Extra Work 9,951.33 0.00 b. Adustment Comp. 3. Materials on Hand 28,866.80 0.00 4. Earned Subject to Retention 759,479.50 107,808.32 5. Mobilization 199,500.00 0.00 6. Total Work Completed 930,112.70 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 958,979.50 107,808.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 107,808.32