Dept. of Trans. PROGRESS Serial No. Contract No. 22-111-09-40 07-319204 PROGRESS PAYMENT VOUCHER %complete: %time: 33% 22% Location: Federal Project: 07-LA-91-6.0/18.6 ACNH-X037(225) Progress payment No. 002 Payment period ending: 04-20-22 CALMEX ENGINEERING INC 2764 SOUTH VISTA AVE BLOOMINGTON CA 92316 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 586,858.62 343,415.58 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 586,858.62 343,415.58 5. Mobilization 146,300.00 30,800.00 6. Total Work Completed 733,158.62 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 733,158.62 374,215.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 374,215.58