Dept. of Trans. PROGRESS Serial No. Contract No. 26-083-07-05 07-319604 PROGRESS PAYMENT VOUCHER %complete: %time: 2% 13% Location: Federal Project: 07-VEN-1-21.3/21.9 BFNH-X111(82) 07-VEN-101-R34.9/R36.1 Progress payment No. 004 Payment period ending: 03-20-26 BEADOR CONSTRUCTION COMPANY INC 2900 BRISTOL ST #D204 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 707,384.00 162,030.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 239,603.01 0.00 4. Earned Subject to Retention 946,987.01 162,030.00 5. Mobilization 6. Total Work Completed 707,384.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 946,987.01 162,030.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 162,030.00