Dept. of Trans. PROGRESS Serial No. Contract No. 24-170-11-37 07-3203U4 PROGRESS PAYMENT VOUCHER %complete: %time: 23% 19% Location: Federal Project: 07-LA-91-R16.6/R16.8 ACIM-X037(232) 07-LA-605-R0.0/R10.4 Progress payment No. 010 Payment period ending: 06-20-24 RASMUSSEN/VANGUARD 28548 LIVINGSTON AVE VALENCIA CA 91355 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,639,255.70 2,113,764.00 2. a. Extra Work 418,448.86 94,872.69 b. Adustment Comp. 3. Materials on Hand 280,793.95 0.00 4. Earned Subject to Retention 8,338,498.51 2,208,636.69 5. Mobilization 3,600,000.00 0.00 6. Total Work Completed 11,657,704.56 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,938,498.51 2,208,636.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,208,636.69