Dept. of Trans. PROGRESS Serial No. Contract No. 24-354-12-09 07-3203U4 PROGRESS PAYMENT VOUCHER %complete: %time: 57% 33% Location: Federal Project: 07-LA-91-R16.6/R16.8 ACIM-X037(232) 07-LA-605-R0.0/R10.4 Progress payment No. 016 Payment period ending: 12-20-24 RASMUSSEN/VANGUARD 28548 LIVINGSTON AVE VALENCIA CA 91355 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,738,597.86 1,428,896.38 2. a. Extra Work 1,388,930.43 40,858.68 b. Adustment Comp. 3. Materials on Hand 555,531.77 186,437.52 4. Earned Subject to Retention 25,683,060.06 1,656,192.58 5. Mobilization 4,800,000.00 240,000.00 6. Total Work Completed 29,927,528.29 7. Deductions -84,600.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 30,398,460.06 1,886,192.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,886,192.58