Dept. of Trans. PROGRESS Serial No. Contract No. 25-055-09-38 07-3203U4 PROGRESS PAYMENT VOUCHER %complete: %time: 61% 36% Location: Federal Project: 07-LA-91-R16.6/R16.8 ACIM-X037(232) 07-LA-605-R0.0/R10.4 Progress payment No. 018 Payment period ending: 02-20-25 RASMUSSEN/VANGUARD 28548 LIVINGSTON AVE VALENCIA CA 91355 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,260,605.93 1,948,366.04 2. a. Extra Work 1,407,247.81 1,718.30 b. Adustment Comp. 3. Materials on Hand 216,014.36 -19,903.25 4. Earned Subject to Retention 27,883,868.10 1,930,181.09 5. Mobilization 4,800,000.00 0.00 6. Total Work Completed 32,467,853.74 7. Deductions -84,600.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 32,599,268.10 1,930,181.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,930,181.09