Dept. of Trans. PROGRESS Serial No. Contract No. 25-167-11-36 07-3203U4 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 45% Location: Federal Project: 07-LA-91-R16.6/R16.8 ACIM-X037(232) 07-LA-605-R0.0/R10.4 Progress payment No. 022 Payment period ending: 06-20-25 RASMUSSEN/VANGUARD 28548 LIVINGSTON AVE VALENCIA CA 91355 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 35,002,511.23 841,534.09 2. a. Extra Work 1,717,324.86 1,074.79 b. Adustment Comp. 117,025.79 25,240.58 3. Materials on Hand 300,290.88 57,743.25 4. Earned Subject to Retention 37,137,152.76 925,592.71 5. Mobilization 4,800,000.00 0.00 6. Total Work Completed 41,636,861.88 7. Deductions -24,600.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 41,912,552.76 925,592.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 925,592.71