Dept. of Trans. PROGRESS Serial No. Contract No. 23-050-15-08 07-322404 PROGRESS PAYMENT VOUCHER %complete: %time: 10% 17% Location: Federal Project: 07-LA-134-R12.6/R12.9 NONE Progress payment No. 003 Payment period ending: 02-20-23 BEADOR CONSTRUCTION COMPANY INC 2900 BRISTOL ST #D204 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 299,053.60 -13,700.00 2. a. Extra Work 18,429.46 18,429.46 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 317,483.06 4,729.46 5. Mobilization 303,674.25 0.00 6. Total Work Completed 621,157.31 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 621,157.31 4,729.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,729.46