Dept. of Trans. PROGRESS Serial No. Contract No. 25-167-12-53 07-322504 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 72% Location: Federal Project: 07-LA-103-0.1/0.1 BFNH-P103(6) Progress payment No. 011 Payment period ending: 06-20-25 BEADOR CONSTRUCTION COMPANY INC 2900 BRISTOL ST #D204 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,076,557.35 1,188,382.58 2. a. Extra Work 761,539.31 0.00 b. Adustment Comp. 3. Materials on Hand 38,633.38 0.00 4. Earned Subject to Retention 16,876,730.04 1,188,382.58 5. Mobilization 1,875,000.00 0.00 6. Total Work Completed 18,713,096.66 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,751,730.04 1,188,382.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,188,382.58