Dept. of Trans. PROGRESS Serial No. Contract No. 24-110-15-41 07-322604 PROGRESS PAYMENT VOUCHER %complete: %time: PEP SAT Location: Federal Project: 07-LA-210-R41.3/R44.6 ACIM-2101(856) Progress payment No. 021 Payment period ending: 04-20-24 SEMA CONSTRUCTION INC 9810 SCRIPPS LAKE DR #C SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,949,393.25 18,568.68 2. a. Extra Work 105,790.82 0.00 b. Adustment Comp. 57,644.26 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,112,828.33 18,568.68 5. Mobilization 333,760.61 0.00 6. Total Work Completed 3,446,588.94 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,446,588.94 18,568.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 18,568.68