Dept. of Trans. PROGRESS Serial No. Contract No. 22-325-11-43 07-323104 PROGRESS PAYMENT VOUCHER %complete: %time: 32% 8% Location: Federal Project: 07-LA-210-R36.0/R40.6 ACIM-2101(855) Progress payment No. 003 Payment period ending: 11-20-22 ORTIZ ENTERPRISES INC 6 CUSHING #200 IRVINE CA 926184221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 681,447.00 494,034.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 681,447.00 494,034.00 5. Mobilization 266,000.00 126,000.00 6. Total Work Completed 947,447.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 947,447.00 620,034.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 620,034.00