Dept. of Trans. PROGRESS Serial No. Contract No. 23-354-09-34 07-323304 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 100% Location: Federal Project: 07-LA-60-R28.0/R30.4 ACNH-P060(162) Progress payment No. 020 Payment period ending: 12-20-23 ACCU CONSTRUCTION INC 14751 PLAZA DRIVE #L TUSTIN CA 92780 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,774,878.10 12,180.00 2. a. Extra Work 43,025.82 0.00 b. Adustment Comp. 99,451.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,917,354.92 12,180.00 5. Mobilization 100,000.00 0.00 6. Total Work Completed 3,017,354.92 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,017,354.92 12,180.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 12,180.00