Dept. of Trans. PROGRESS Serial No. Contract No. 22-202-14-40 07-324404 PROGRESS PAYMENT VOUCHER %complete: %time: 10% 45% Location: Federal Project: 07-LA-22-0.0/1.5 NONE Progress payment No. 003 Payment period ending: 07-20-22 SULLY-MILLER CONTRACTING CO 135 S STATE COLLEGE BLVD #400 BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 240,210.62 131,980.62 2. a. Extra Work 13,385.95 13,385.95 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 253,596.57 145,366.57 5. Mobilization 239,484.84 239,484.84 6. Total Work Completed 493,081.41 7. Deductions 0.00 5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 493,081.41 389,851.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 389,851.41