Dept. of Trans. PROGRESS Serial No. Contract No. 24-081-21-17 07-324904 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 87% Location: Federal Project: 07-LA-5-19.7/36.0 NONE Progress payment No. 009 Payment period ending: 03-20-24 STACY AND WITBECK INC 2800 HARBOR BAY PKWY ALAMEDA CA 94502 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,088,607.28 61,594.00 2. a. Extra Work 11,524.26 6,338.14 b. Adustment Comp. 3. Materials on Hand 585,101.86 -30,017.20 4. Earned Subject to Retention 2,685,233.40 37,914.94 5. Mobilization 480,000.00 0.00 6. Total Work Completed 2,580,131.54 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,165,233.40 37,914.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 37,914.94