Dept. of Trans. PROGRESS Serial No. Contract No. 24-205-10-45 07-3255U4 PROGRESS PAYMENT VOUCHER %complete: %time: 31% 27% Location: Federal Project: 07-LA-605-R20.2/R26.0 ACIM-6052(7) Progress payment No. 010 Payment period ending: 07-20-24 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,938,978.06 870,012.80 2. a. Extra Work 205,446.61 18,181.59 b. Adustment Comp. 36,031.81 0.00 3. Materials on Hand 97,059.00 -26,905.00 4. Earned Subject to Retention 5,277,515.48 861,289.39 5. Mobilization 237,500.00 0.00 6. Total Work Completed 5,417,956.48 7. Deductions -23,471.50 -23,471.50 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,491,543.98 837,817.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 837,817.89