Dept. of Trans. PROGRESS Serial No. Contract No. 25-199-14-59 07-3255U4 PROGRESS PAYMENT VOUCHER %complete: %time: 69% 57% Location: Federal Project: 07-LA-605-R20.2/R26.0 ACIM-6052(7) Progress payment No. 022 Payment period ending: 07-20-25 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,667,229.44 2,408,272.78 2. a. Extra Work 471,755.97 86,874.44 b. Adustment Comp. 100,821.55 0.00 3. Materials on Hand 149,784.00 -28,566.00 4. Earned Subject to Retention 12,389,590.96 2,466,581.22 5. Mobilization 250,000.00 0.00 6. Total Work Completed 12,489,806.96 7. Deductions -23,471.50 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,616,119.46 2,466,581.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,466,581.22