Dept. of Trans. PROGRESS Serial No. Contract No. 25-295-13-08 07-3255U4 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 65% Location: Federal Project: 07-LA-605-R20.2/R26.0 ACIM-6052(7) Progress payment No. 025 Payment period ending: 10-20-25 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,615,576.43 978,830.11 2. a. Extra Work 646,190.39 13,593.92 b. Adustment Comp. 116,987.89 0.00 3. Materials on Hand 53,190.00 -17,415.00 4. Earned Subject to Retention 15,431,944.71 975,009.03 5. Mobilization 250,000.00 0.00 6. Total Work Completed 15,628,754.71 7. Deductions -23,471.50 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,658,473.21 975,009.03 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 975,009.03