Dept. of Trans. PROGRESS Serial No. Contract No. 20-359-11-46 07-325704 PROGRESS PAYMENT VOUCHER %complete: %time: 67% 77% Location: Federal Project: 07-LA-5-1.7/1.7 NONE Progress payment No. 018 Payment period ending: 12-20-20 SPECTRUM CONSTRUCTION GROUP INC 32 EDELMAN IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,820,668.48 630,569.60 2. a. Extra Work 26,875.10 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 12,847,543.58 630,569.60 5. Mobilization 6. Total Work Completed 12,847,543.58 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,847,543.58 630,569.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 630,569.60