Dept. of Trans. PROGRESS Serial No. Contract No. 21-141-11-12 07-325704 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 100% Location: Federal Project: 07-LA-5-1.7/1.7 NONE Progress payment No. 023 Payment period ending: 05-20-21 SPECTRUM CONSTRUCTION GROUP INC 32 EDELMAN IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,665,780.48 779,300.00 2. a. Extra Work 358,901.35 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 17,024,681.83 779,300.00 5. Mobilization 6. Total Work Completed 17,024,681.83 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,024,681.83 779,300.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 779,300.00