Dept. of Trans. PROGRESS Serial No. Contract No. 19-112-14-32 07-326104 PROGRESS PAYMENT VOUCHER %complete: %time: 77% 53% Location: Federal Project: 07-LA-47-0.8/0.8 ACNH-P047(13) Progress payment No. 009 Payment period ending: 04-20-19 BEADOR CONSTRUCTION COMPANY 26320 LESTER CIR CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 986,112.34 52,664.34 2. a. Extra Work 12,425.56 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 998,537.90 52,664.34 5. Mobilization 112,600.00 0.00 6. Total Work Completed 1,111,137.90 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,111,137.90 52,664.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 52,664.34