Dept. of Trans. PROGRESS Serial No. Contract No. 22-234-13-53 07-327204 PROGRESS PAYMENT VOUCHER %complete: %time: 29% 33% Location: Federal Project: 07-LA-1-R34.5/35.2 NONE Progress payment No. 010 Payment period ending: 08-20-22 DBX INC 42024 AVENIDA ALVARADO #A TEMECULA CA 92590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,218,723.34 1,096,854.78 2. a. Extra Work 26,197.88 0.00 b. Adustment Comp. 3. Materials on Hand 183,806.00 -141,222.00 4. Earned Subject to Retention 3,428,727.22 955,632.78 5. Mobilization 275,500.00 0.00 6. Total Work Completed 3,520,421.22 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,704,227.22 955,632.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 955,632.78