Dept. of Trans. PROGRESS Serial No. Contract No. 23-143-09-19 07-327304 PROGRESS PAYMENT VOUCHER %complete: %time: 35% 30% Location: Federal Project: 07-LA-103-0.1/0.1 ACNH-P103(5) Progress payment No. 010 Payment period ending: 05-20-23 SHIMMICK CONSTRUCTION CO. INC 530 TECHNOLOGY DRIVE #300 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,910,748.46 289,622.46 2. a. Extra Work 400,026.51 41,660.80 b. Adustment Comp. 3. Materials on Hand 96,544.94 0.00 4. Earned Subject to Retention 3,407,319.91 331,283.26 5. Mobilization 1,140,000.00 0.00 6. Total Work Completed 4,450,774.97 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,547,319.91 331,283.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 331,283.26