Dept. of Trans. PROGRESS Serial No. Contract No. 25-112-08-34 07-330304 PROGRESS PAYMENT VOUCHER %complete: %time: 84% 90% Location: Federal Project: 07-LA-10-22.0/30.8 HSIM-101(857) Progress payment No. 016 Payment period ending: 04-20-25 FEC FUTURE CONTRACTORS AND ENGINEERS INC 184 TECHNOLOGY DRIVE #205 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,017,514.72 256,119.73 2. a. Extra Work 165,869.68 0.00 b. Adustment Comp. 3. Materials on Hand 14,086.10 0.00 4. Earned Subject to Retention 5,197,470.50 256,119.73 5. Mobilization 702,000.00 0.00 6. Total Work Completed 5,885,384.40 7. Deductions -176,917.83 -2,172.40 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,722,552.67 253,947.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 253,947.33