Dept. of Trans. PROGRESS Serial No. Contract No. 22-353-14-50 07-330504 PROGRESS PAYMENT VOUCHER %complete: %time: 16% 3% Location: Federal Project: 07-LA-710-R15.1/21.9 ACIM-7101(843) Progress payment No. 001 Payment period ending: 12-20-22 LANDSCAPE SUPPORT SERVICES INC PO BOX 55307 SHERMAN OAKS CA 91413 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 315,611.59 315,611.59 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 315,611.59 315,611.59 5. Mobilization 107,691.00 107,691.00 6. Total Work Completed 423,302.59 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 423,302.59 423,302.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 423,302.59