Dept. of Trans. PROGRESS Serial No. Contract No. 23-325-16-17 07-3311U4 PROGRESS PAYMENT VOUCHER %complete: %time: 25% 46% Location: Federal Project: 07-VEN-101-0.2/40.8 ACNH-X111(79) Progress payment No. 012 Payment period ending: 11-20-23 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,641,899.76 581,322.70 2. a. Extra Work 114,451.43 0.00 b. Adustment Comp. 3. Materials on Hand 1,881,124.00 -67,092.00 4. Earned Subject to Retention 7,637,475.19 514,230.70 5. Mobilization 783,750.00 0.00 6. Total Work Completed 6,540,101.19 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,421,225.19 514,230.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 514,230.70