Dept. of Trans. PROGRESS Serial No. Contract No. 23-354-14-55 07-3311U4 PROGRESS PAYMENT VOUCHER %complete: %time: 28% 50% Location: Federal Project: 07-VEN-101-0.2/40.8 ACNH-X111(79) Progress payment No. 013 Payment period ending: 12-20-23 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,365,843.92 723,944.16 2. a. Extra Work 224,931.74 110,480.31 b. Adustment Comp. 3. Materials on Hand 1,797,664.00 -83,460.00 4. Earned Subject to Retention 8,388,439.66 750,964.47 5. Mobilization 783,750.00 0.00 6. Total Work Completed 7,374,525.66 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 9,172,189.66 750,964.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 750,964.47