Dept. of Trans. PROGRESS Serial No. Contract No. 24-086-11-53 07-3311U4 PROGRESS PAYMENT VOUCHER %complete: %time: 33% 60% Location: Federal Project: 07-VEN-101-0.2/40.8 ACNH-X111(79) Progress payment No. 016 Payment period ending: 03-20-24 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,520,360.11 276,376.50 2. a. Extra Work 374,397.09 72,445.23 b. Adustment Comp. 3. Materials on Hand 1,861,595.00 -70,120.00 4. Earned Subject to Retention 9,756,352.20 278,701.73 5. Mobilization 783,750.00 0.00 6. Total Work Completed 8,678,507.20 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,540,102.20 278,701.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 278,701.73