Dept. of Trans. PROGRESS Serial No. Contract No. 24-114-09-02 07-3311U4 PROGRESS PAYMENT VOUCHER %complete: %time: 35% 63% Location: Federal Project: 07-VEN-101-0.2/40.8 ACNH-X111(79) Progress payment No. 017 Payment period ending: 04-20-24 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,025,260.81 504,900.70 2. a. Extra Work 374,397.09 0.00 b. Adustment Comp. 3. Materials on Hand 1,821,520.00 -40,075.00 4. Earned Subject to Retention 10,221,177.90 464,825.70 5. Mobilization 783,750.00 0.00 6. Total Work Completed 9,183,407.90 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,004,927.90 464,825.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 464,825.70