Dept. of Trans. PROGRESS Serial No. Contract No. 24-169-13-55 07-3311U4 PROGRESS PAYMENT VOUCHER %complete: %time: 40% 73% Location: Federal Project: 07-VEN-101-0.2/40.8 ACNH-X111(79) Progress payment No. 019 Payment period ending: 06-20-24 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,288,331.70 555,772.15 2. a. Extra Work 388,655.60 14,258.51 b. Adustment Comp. 3. Materials on Hand 1,781,744.00 -2,480.00 4. Earned Subject to Retention 11,458,731.30 567,550.66 5. Mobilization 783,750.00 0.00 6. Total Work Completed 10,460,737.30 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,242,481.30 567,550.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 567,550.66