Dept. of Trans. PROGRESS Serial No. Contract No. 24-261-15-41 07-3311U4 PROGRESS PAYMENT VOUCHER %complete: %time: 46% 88% Location: Federal Project: 07-VEN-101-0.2/40.8 ACNH-X111(79) Progress payment No. 021 Payment period ending: 09-20-24 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,812,431.82 810,037.02 2. a. Extra Work 484,493.37 59,714.38 b. Adustment Comp. 3. Materials on Hand 3,853,355.00 2,198,912.00 4. Earned Subject to Retention 15,150,280.19 3,068,663.40 5. Mobilization 825,000.00 41,250.00 6. Total Work Completed 12,121,925.19 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,975,280.19 3,109,913.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,109,913.40