Dept. of Trans. PROGRESS Serial No. Contract No. 25-112-14-51 07-3311U4 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 94% Location: Federal Project: 07-VEN-101-0.2/40.8 ACNH-X111(79) Progress payment No. 023 Payment period ending: 04-20-25 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,429,467.10 355,063.78 2. a. Extra Work 1,330,700.51 397,009.23 b. Adustment Comp. 3. Materials on Hand 1,255,333.57 -52,689.06 4. Earned Subject to Retention 16,015,501.18 699,383.95 5. Mobilization 825,000.00 0.00 6. Total Work Completed 15,585,167.61 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,840,501.18 699,383.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 699,383.95