Dept. of Trans. PROGRESS Serial No. Contract No. 25-295-13-08 07-3311U4 PROGRESS PAYMENT VOUCHER %complete: %time: 69% 100% Location: Federal Project: 07-VEN-101-0.2/40.8 ACNH-X111(79) Progress payment No. 029 Payment period ending: 10-20-25 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,964,355.72 276,903.84 2. a. Extra Work 2,013,684.36 267,900.17 b. Adustment Comp. 3. Materials on Hand 904,073.45 -31,424.17 4. Earned Subject to Retention 18,882,113.53 513,379.84 5. Mobilization 825,000.00 0.00 6. Total Work Completed 18,803,040.08 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 19,707,113.53 513,379.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 513,379.84