Dept. of Trans. PROGRESS Serial No. Contract No. 25-354-10-35 07-3311U4 PROGRESS PAYMENT VOUCHER %complete: %time: 72% 100% Location: Federal Project: 07-VEN-101-0.2/40.8 ACNH-X111(79) Progress payment No. 031 Payment period ending: 12-20-25 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,672,482.96 23,594.50 2. a. Extra Work 2,078,704.39 8,479.48 b. Adustment Comp. 3. Materials on Hand 826,490.88 -5,517.61 4. Earned Subject to Retention 19,577,678.23 26,556.37 5. Mobilization 825,000.00 0.00 6. Total Work Completed 19,576,187.35 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 20,402,678.23 26,556.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 26,556.37