Dept. of Trans. PROGRESS Serial No. Contract No. 23-170-14-59 07-331804 PROGRESS PAYMENT VOUCHER %complete: %time: 20% 7% Location: Federal Project: 07-LA-710-26.0/R26.7 ACIM-X037(229) Progress payment No. 006 Payment period ending: 06-20-23 GRIFFITH COMPANY 1128 CARRIER PKWY AV BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 442,316.33 123,712.25 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 11,673.00 -5,735.00 4. Earned Subject to Retention 453,989.33 117,977.25 5. Mobilization 93,750.00 0.00 6. Total Work Completed 536,066.33 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 547,739.33 117,977.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 117,977.25