Dept. of Trans. PROGRESS Serial No. Contract No. 22-230-13-56 07-332604 PROGRESS PAYMENT VOUCHER %complete: %time: 75% 41% Location: Federal Project: 07-LA-10-R12.4/14.9 SIMG-010-1(854) Progress payment No. 019 Payment period ending: 08-20-22 CHUMO CONSTRUCTION INC 14425 JOANBRIDGE ST BALDWIN PARK CA 917061747 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,850,214.31 659,846.71 2. a. Extra Work 426,903.20 17,975.75 b. Adustment Comp. 37,380.04 0.00 3. Materials on Hand 690,729.00 84,116.00 4. Earned Subject to Retention 11,005,226.55 761,938.46 5. Mobilization 1,400,000.00 0.00 6. Total Work Completed 11,714,497.55 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,405,226.55 761,938.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 761,938.46