Dept. of Trans. PROGRESS Serial No. Contract No. 22-297-09-45 07-332604 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 45% Location: Federal Project: 07-LA-10-R12.4/14.9 SIMG-010-1(854) Progress payment No. 021 Payment period ending: 10-20-22 CHUMO CONSTRUCTION INC 14425 JOANBRIDGE ST BALDWIN PARK CA 917061747 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,057,636.96 1,215,337.38 2. a. Extra Work 482,696.79 47,274.97 b. Adustment Comp. 67,963.70 0.00 3. Materials on Hand 163,081.00 -391,433.00 4. Earned Subject to Retention 12,771,378.45 871,179.35 5. Mobilization 1,400,000.00 0.00 6. Total Work Completed 14,008,297.45 7. Deductions -2,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,169,378.45 871,179.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 871,179.35